Biomass project
07 May 2024
Work is progressing at Clairefontaine Papermills!
Our biomass project is making good progress, as the boiler is now in the installation phase.
Civil engineering operations have progressed right on schedule, allowing the boiler manufacturer to install the main equipment components.
The heating plant has taken on a whole new look, with the installation of the roof and cladding to protect the workers from rain and winds.
Civil engineering work is now focused on the silo building, and the wood handling equipment is slated for installation this summer.
We'll be sure to keep you posted on the progress of the work!